Commit message (Collapse) | Author | Age | |
---|---|---|---|
* | Apply speed restriction 0.5 indexes later, do not cap tarvelocity by ↵ | orwell96 | 2018-12-04 |
| | | | | speed_restriction | ||
* | Do not set speed_restriction for npr | orwell96 | 2018-12-04 |
| | |||
* | Added on_train_approach callback, non-permanent external LZB brakepoints and ↵ | orwell96 | 2018-11-29 |
| | | | | | | basis for "stop rails" Stop rails ATM use the aforementioned things to add a pointwise "2" speed restriction. Seems to work. | ||
* | Permit basic signal aspect setting | orwell96 | 2018-11-19 |
| | | | | (basically only usable with Ks signals, because they're the only signals supporting slow move and/or shunt move | ||
* | Replace "Allow accelereting train towards signal" | orwell96 | 2018-10-30 |
| | | | | This is a better implementation of the same goal. The last commit caused trains to overrun the IP sometimes. Haven't noticed so far with this approach | ||
* | Make fillout_aspect also fill "info" field | orwell96 | 2018-10-30 |
| | |||
* | Do not allow static signals for routesetting | orwell96 | 2018-10-30 |
| | |||
* | Do not print "couldn't determine section" warning when all traverser ends ↵ | orwell96 | 2018-10-29 |
| | | | | were end-of-track | ||
* | Allow to accelerate trains slowly towards red signals from stand. | orwell96 | 2018-10-29 |
| | | | | Previously, it was impossible to accelerate a standing train once it was ~10m in front of a red signal. | ||
* | Fix typo in signal assignment, causing crash | orwell96 | 2018-10-29 |
| | |||
* | Miscellaneous routesetting fixes | orwell96 | 2018-10-29 |
| | | | | | | | - Move handling of "route_committed" to the routesetting function - Put aspect in every TCBS on the way - Add "route_origin" to TCBS fields to prevent subroute cancelling - Cancel entire route when another train enters from the wrong TCB | ||
* | Fix signal_get_aspect() | orwell96 | 2018-10-29 |
| | | | | Had a series of bugs as result, like auto-clearing IPs and not-working lzb | ||
* | Add Interlocking Tool to inspect route locks | orwell96 | 2018-10-26 |
| | |||
* | Add "Reset track section" function | orwell96 | 2018-10-26 |
| | |||
* | Fix demo signals | orwell96 | 2018-10-25 |
| | |||
* | Add doc for supported_aspects, improve other doc and aspect autofill | orwell96 | 2018-10-25 |
| | |||
* | Display route_rsn when denying routesetting by subroute locked. | orwell96 | 2018-10-25 |
| | |||
* | Improve ATC-LZB-User control interaction, smoothen LZB control operations | orwell96 | 2018-10-17 |
| | | | | (prevent flickering view when atc battles against lzb) | ||
* | Actually allow what manual promises (setting IP on non-assigned signals) | orwell96 | 2018-10-17 |
| | |||
* | Remote Routesetting from Onboard Computer | orwell96 | 2018-10-10 |
| | | | | + Fix lzb oncoming item deletion/speed restriction | ||
* | Properly implement invalidate_all_paths, recheck lzb on aspect change | orwell96 | 2018-10-10 |
| | |||
* | Add signal safety control override, restructure control system | orwell96 | 2018-10-10 |
| | |||
* | Make signal influence point (~halt point) specifiable | orwell96 | 2018-10-09 |
| | | | | Also extend signal api necessarily | ||
* | Improve route programming: | orwell96 | 2018-10-07 |
| | | | | | | | - Formspec for TCBs instead of unhandy chatcommands - Ability to advance route over the next secction without punching end - Better visualization - Ability to route into dead-end sections | ||
* | Fix route programming lock-placement | orwell96 | 2018-09-28 |
| | |||
* | Add LuaAutomation interface functions for interlocking routesetting and ↵ | orwell96 | 2018-08-24 |
| | | | | | | aspect requesting. This allows to incorporate interlocking to automated systems | ||
* | Move passive API to the advtrains core | orwell96 | 2018-08-16 |
| | | | | to remove dependency of interlocking on luaautomation | ||
* | Fix various bugs found while testing | orwell96 | 2018-08-13 |
| | |||
* | Add 'interlocking' privilege and add security checks | orwell96 | 2018-08-12 |
| | |||
* | Automatic working (re-set certain route on train pass) | orwell96 | 2018-08-12 |
| | |||
* | fix digging unconfigured tcbs | orwell96 | 2018-08-12 |
| | |||
* | Signal aspect handling, make default signals compatible, fix signal digging | orwell96 | 2018-08-12 |
| | |||
* | Add routesetting callbacks. | orwell96 | 2018-08-12 |
| | | | | Now, only the signal aspect setting is still missing | ||
* | Uncommitted route handling (update_route function) | orwell96 | 2018-08-03 |
| | |||
* | Implement routesetting | orwell96 | 2018-07-21 |
| | | | | Missing things: signal aspect updating, waiting routes handling, management /info tool | ||
* | Change stuff on route programming, begin routesetting | orwell96 | 2018-07-17 |
| | |||
* | Basic route management from signalling formspec | orwell96 | 2018-07-04 |
| | |||
* | Signal assignment and route programming procedure | orwell96 | 2018-07-04 |
| | |||
* | Implement trains blocking sections | orwell96 | 2018-06-29 |
| | |||
* | get_ts_at_pos(), file for train-related stuff | orwell96 | 2018-06-29 |
| | |||
* | Complete Track Section handling, incl. removing tcb's and marker entities | orwell96 | 2018-06-26 |
| | |||
* | Add track section concept and rework TCB design, implement new linking behavior | orwell96 | 2018-06-21 |
| | |||
* | Add Track Circuit Breaks (TCBs), Database and Track Circuit Setup | orwell96 | 2018-06-20 |
| | | | | Does not get saved yet. | ||
* | Interlocking: Create demo signals, signal API and model for TCB configurer node | orwell96 | 2018-06-19 |
| | |||
* | Draft of interlocking system | orwell96 | 2018-06-14 |